Benestad

In May 2025, BayWa r.e. Nordic received a building permit to construct a 60 MW battery storage facility in Alvesta Municipality. The site, around 1 hectare in size, was chosen due to its grid connection availability and minimal environmental and cultural impact.

The facility will temporarily store electricity and contribute to grid stability by balancing fluctuations in power generation and consumption.

Design planning and grid connection preparations are ongoing. The battery storage facility is scheduled for commissioning in 2029.

Alvesta

Municipality

Approx. 1 hectare

Area

Approx. 60 MWp

Power

Project Location