SwedenBayWa r.e. has been responsible for the design, development, procurement, management, finance, construction project management and sale of Slageryd. The wind farm is located about 2 kilometers north west of Slageryd.
The wind farm consists of six wind turbines of the model Nordex N131 3.9 MW and is rated at a total of 23.4 MW. The plant is expected to produce 71,000 MWh per year, which is equivalent to the annual electricity consumption (heating excluded) of 14,200 residential houses.
Location | Karsholm, Kristianstad |
---|---|
Number of turbines | 5 |
Output | 10.25 MW |
Annual production | 28 GWh |
Technology | REpower MM92 |
Hub height | 100 m |
Rotor diameter | 92 m |
Total height | 146 m |
Commissioned | 2012 |
Manager | Christian Eriksson |